A Midwestern Ethanol plant installed a Gamajet E-Z8 and conducted a before and after analysis:
|
Before Alfa Laval |
After Alfa Laval |
Cleaning time per batch |
3 hours |
1.5 hours |
Hours lost to machine maintenance per year |
56 hours |
0 hours |
Batches lost to contamination |
1 |
0 |
The company also reported that GJ 8 enabled them to produce 3.35 additional batches per year.